CFE has put a new transformer into service at the Parque Industrial Kalos substation in Santa Catarina, Nuevo León. EL NORTE reported that the eight-month project cost MX$84 million.
Milenio reported that the new unit has 30 MVA of capacity and that CFE expects more than 15,000 residential and industrial users to benefit. The reports do not identify individual companies among those users or estimate a change in outage frequency.
- Location: Parque Industrial Kalos substation, Santa Catarina.
- Investment: MX$84 million.
- Construction period: eight months.
- New transformer capacity: 30 MVA.
- Expected direct beneficiaries: more than 15,000 residential and industrial users, according to CFE as reported by Milenio.