Nuevo León mobility secretary Hernán Villarreal said repairs to the storm-drain system near Avenida Venustiano Carranza in Monterrey would begin after the main work at Gonzalitos. Milenio reported on October 27 that the state had not set a date.
Milenio traced the drainage damage to Metro Line 4 construction near Constitución and Venustiano Carranza. The state and Monterrey agreed to address Gonzalitos first, then return to the drain; the reported sequence is intended to avoid disrupting both traffic areas at once.
El Norte reported that Mota-Engil, the contractor building the new Metro lines, would cover the repair cost. It gave no amount, and neither outlet reported a start or completion date for the Venustiano Carranza work.
- Location: storm-drain system near Avenida Venustiano Carranza and Constitución, Monterrey.
- Associated project: Metro Line 4 construction.
- Work sequence: Gonzalitos traffic work first, then the drain repair.
- Repair cost: Mota-Engil will cover it, according to El Norte; no amount was disclosed.
- Timing: no start or completion date was reported.