Torre Rise reached level 101 with its final concrete slab pour in Monterrey on October 31, completing the tower’s concrete phase. EL NORTE reported the milestone on November 1; ABC Noticias reported the level milestone on October 31.
That is not the opening. ABC Noticias reports the finished structure is expected to reach 484 meters including the roughly 71-meter steel spire now being fabricated; installation is expected to start in November. The outlet estimates project completion for mid-2027, with interior systems, finishes and equipment still to come.
- Location: Monterrey, Nuevo León
- Milestone: final concrete slab poured at level 101 on October 31
- Planned overall height: 484 meters, including the architectural spire
- Building configuration: 96 above-ground floors and five basement levels
- Spire: approximately 71 meters; installation expected to begin in November
- Project completion estimate: mid-2027
